Sizing Estimation
Based on the problem 1's description from the SDLC
activity:
- Apply the intuitive method in estimating the software size
- Apply the historical method in estimating the software size
- Apply the function point method in estimating the software size
Which technique is more appropriate for this problem description? Why?
Come up with one scenario for each of the following:
- When the intuitive method is the best choice in estimating sizing
- When the historical method is the best choice in estimating sizing
- When the function point method is the best choice in estimating sizing
And explain why that method is better than the other two.
Cost (Effort) Estimation
Based on the problem 1's description from the SDLC
activity, apply the COCOMO I model in estimating the software cost.
Estimation for A2
If time allows, repeat the above activities but base it on your A2
description.